An Electrical Installation Condition Report, usually shortened to EICR, assesses the condition of a fixed electrical installation at the time of inspection. The quotation is mainly influenced by the number of circuits, the size and use of the property, access and the quality of the existing records.

A low-cost inspection that allows too little time can be a false economy. The electrician needs enough time to inspect, test, record results and identify observations accurately. An EICR is a report on condition, not a pass certificate that can be promised in advance.

What is actually inspected during an EICR?

The inspection looks at the fixed wiring, consumer unit or distribution boards, protective devices, earthing and bonding, accessories and a representative sample of the installation. Electrical tests are used to assess matters that cannot be judged by appearance alone.

The extent of inspection and testing should be agreed before work begins. Limitations may be necessary where areas are inaccessible, sensitive equipment cannot be disconnected or parts of a commercial installation must remain energised. Any limitation should be recorded on the report rather than quietly omitted.

  • Adequacy of earthing, bonding and protection against electric shock.
  • Condition and suitability of the consumer unit and protective devices.
  • Circuit continuity, insulation resistance and polarity.
  • RCD operation and other protective-device testing where applicable.
  • Signs of damage, overheating, deterioration or unsuitable alterations.
  • Identification, schedules, warning labels and previous test information.

What affects the cost of an EICR?

Bedrooms are sometimes used as a rough pricing guide for houses, but the circuit count is more meaningful. A compact property with electric heating, an outbuilding, solar panels and several distribution boards can take longer to test than a larger home with a simple installation.

Access is another major factor. Testing is faster when the consumer unit, sockets and equipment are accessible and the property can tolerate planned interruptions. It takes longer when furniture blocks accessories, circuits are poorly labelled or tenants and business operations must be coordinated.

  • Number of consumer units, distribution boards and final circuits.
  • Domestic, rented, commercial or industrial use.
  • Age, complexity and apparent condition of the installation.
  • Whether previous circuit schedules and certificates are available.
  • Outbuildings, electric heating, EV charging, solar PV or fixed equipment.
  • Access restrictions and the amount of agreed sampling or limitations.

What should a domestic EICR budget allow?

Current 2026 UK consumer price guides commonly place a straightforward domestic EICR in roughly the £150 to £300 range, with an average figure a little above £200. Smaller, simple installations may cost less, while larger homes, several boards, electric heating or poor circuit records can cost more.

That range should only help with early budgeting. A responsible quotation needs the property type, approximate circuit count, outbuildings, access and reason for the report. Confirm whether VAT is included and remember that remedial work is normally separate.

Does the price include repairs?

Normally, no. An EICR is an inspection and report. It identifies observations and gives them classification codes, but remedial work should be quoted separately so you can see the cost of the report and the cost of repairs independently.

A minor item may sometimes be corrected during the visit if you have authorised it, the part is available and it does not compromise the inspection programme. It should still be recorded clearly. Larger remedial work requires an agreed scope and suitable certification after completion.

Understanding C1, C2, C3 and FI codes

A C1 observation means danger is present and immediate action is required. C2 means a potentially dangerous condition has been identified and urgent remedial action is needed. FI means further investigation is required without delay because the inspector could not determine safety within the agreed inspection.

C3 identifies an improvement that is recommended but does not, on its own, make the report unsatisfactory. A report with one or more C1, C2 or FI observations is assessed as unsatisfactory. The wording beside each code matters because it explains the actual defect and location.

  • C1: danger present, with immediate action required.
  • C2: potentially dangerous, with urgent remedial action required.
  • FI: further investigation required without delay.
  • C3: improvement recommended.

How to prepare for the inspection

Make the consumer unit, sockets, switches and fixed equipment accessible. Tell occupants that power will be interrupted and make arrangements for alarms, servers, medical equipment, refrigeration or home-working equipment that cannot be unexpectedly switched off.

Send previous reports, certificates, circuit schedules and details of alterations before the visit where possible. Good records do not replace testing, but they help the inspector understand the installation and investigate changes more efficiently.

Related electrical work

Services mentioned in this guide

Further information

These independent sources provide additional safety or regulatory information:

GOV.UK: electrical safety standards in rented propertiesElectrical Safety First: landlord electrical safetyCheckatrade: 2026 EICR cost information

If you need an electrician

What to send us

Describe the issue

Tell us what is happening, which part of the property is affected and whether any recent work may be connected.

Share useful details

Photographs, equipment model numbers and existing certificates help us understand the likely scope before a visit.

Agree the next step

We will explain whether the job needs an inspection, fault-finding appointment or site survey before quotation.

Chelmsford Electrical

Contact us about the work

Send us the property details and a short description. We will contact you to discuss it.

We use these details only to respond to your enquiry.
Get a quote